Historic sewer discovery delayed 16th Street project a year, cost $18 million
The Denver Auditor recently found significant oversight and contracting problems with the $175.6 million 16th Street Improvement Project, including an $18 million contract increase and a nearly one-year extension that bypassed City Council review. The report also found that inadequate planning for historic brick sewers contributed to the overruns, even after one of the three […]