Historic sewer discovery delayed 16th Street project a year, cost $18 million

Historic sewer discovery delayed 16th Street project a year, cost $18 million

The Denver Auditor recently found significant oversight and contracting problems with the $175.6 million 16th Street Improvement Project, including an $18 million contract increase and a nearly one-year extension that bypassed City Council review. The report also found that inadequate planning for historic brick sewers contributed to the overruns, even after one of the three […]

Original Source

Read the full article at Coloradopolitics →

KhanList aggregates and links to publicly available news content. We do not host full articles from third-party sources. Always verify important information with original sources.